Construction Meeting Updates – December 21

Finals are over, the fall semester is over, and now, finally, the rain is over. The pace is picking up once again. Here are the updates:

*The westerly point of connection (POC) in the northwest section of the steam tunnel has been tied in. The easterly POC was being tied in this afternoon.

Westerly POC.

Easterly POC.

*Testing of the steam pipes is expected to begin tomorrow. Once testing is complete, the pre-cast lids can be placed on the tunnel and backfill can begin. That process is expected to begin next week.

Pre-cast lids were finished in early September.

*Demolition of the Aztec Center’s south wall was completed this afternoon. It wasn’t quite as exciting as the Berlin Wall coming down in 1989, but significant nonetheless. “It was a nice wall,” said excavator operator Patrick Carey.

*Grading of the basement area and work on the northeast section of the steam tunnel will commence soon.

That is all for blog posts in 2011. No construction meeting next Wednesday. Thanks for reading and see you in 2012!

Advertisements

About Lorena

I'm a San Diego native and a proud two-time alumna of the San Diego State University School of Journalism and Media Studies. I currently work as the marketing and communications manager for the Associated Students of SDSU.
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s