Construction Meeting Updates – November 30

On this last day of November, one day shy of the sixth-month anniversary of the groundbreaking, here’s what we got:

*Water is still being pumped out of the basement area. Grading will resume as soon as all of the water is gone.

*Demo of the south wall of the main building is underway.

*Welding of the pipes in the northwest section of the steam tunnel is ongoing. The tie-in could come as soon as Monday, December 12.

*University Mechanical is expected to start its work in the northeast section of the steam tunnel next Monday, beginning with the installation of the roller guides for the pipes. Also, the walls for manhole #11 are expected to be poured this Friday.

Advertisements

About Lorena

I'm a San Diego native and a proud two-time alumna of the San Diego State University School of Journalism and Media Studies. I currently work as the marketing and communications manager for the Associated Students of SDSU.
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s