Construction Meeting Update

From today’s weekly construction meeting:

*Work on the northeast section of the steam tunnel is expected to begin next week. Work can begin once the Student Services West water highline (for fire services only) passes the chlorination test and is connected. As a reminder, all “highline” means is a pipe that is above ground.

*Grading, which is pretty much the prelude to concrete pouring for the foundation, is expected to begin next week.

* The actual steam pipes are expected to arrive on site the week of October 31, when they will start to be placed inside the recently formed tunnel.

*Concrete crushing in Lot W will now extend into next week.

Advertisements

About Lorena

I'm a San Diego native and a proud two-time alumna of the San Diego State University School of Journalism and Media Studies. I currently work as the marketing and communications manager for the Associated Students of SDSU.
This entry was posted in Uncategorized. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s